Desk Bees
person shopping_cart
No results found for ""
← Back to Blog

Safety Signage for New Factory Setup in India: The Complete Procurement Timeline

By Super Admin ·

The New Factory Signage Timeline

Setting up a new factory in India is an intensely coordinated effort — civil construction, utility installation, machine commissioning, workforce recruitment, licence applications, and a hundred other workstreams. Safety signage often falls to the bottom of the list, resulting in a frantic last-minute scramble when the factory inspector visits for the licence or when the customer audit is scheduled. This timeline ensures signage is planned properly.

Phase 1: During Construction (6-3 Months Before Commissioning)

Temporary Construction Signs

  • Construction site safety signs (hard hat, safety shoes, hi-vis)
  • Excavation and fall hazard warnings
  • Heavy vehicle movement signs
  • Contractor safety rules board

Action: Order temporary correx board signs. These will be replaced with permanent signs later.

Architecture/Layout Review

  • Obtain final floor plans from the architect/civil contractor
  • Identify all entry/exit points
  • Map fire extinguisher locations (per fire consultant's plan)
  • Map electrical panel locations
  • Define production zones

Action: Send floor plans to your signage supplier for a comprehensive sign schedule.

Phase 2: Pre-Commissioning (3-1 Month Before)

Permanent Sign Order

  • Finalise sign schedule (type, quantity, size, material, language for every sign)
  • Place order with manufacturer (allow 7-10 working days for custom/bilingual signs)
  • Order mounting hardware

Evacuation Plans

  • Commission evacuation plan boards based on final floor plans
  • Include all exits, fire equipment, assembly points, you-are-here markers

Phase 3: Installation (2-1 Week Before Commissioning)

Installation Priority Order

  1. Fire safety signs first — fire extinguisher, hose reel, call point, exit signs
  2. Emergency signs — exit directions, assembly point, evacuation plans
  3. Zone entry signs — PPE mandatory, restricted area, hazard warnings
  4. Machine-level signs — after machines are installed and commissioned
  5. Information and welfare signs — toilets, drinking water, canteen, first aid

Phase 4: Factory Licence Inspection

When the factory inspector visits for the operating licence under the Factories Act / OSH Code, they check:

  • Fire safety signs per NBC / fire NOC requirements
  • Emergency exit signage (photoluminescent)
  • Zone-wise PPE signage
  • Electrical safety signs
  • Welfare facility signs
  • Assembly point and evacuation plans

Tip: Schedule your signage installation before the inspector visit. "Signs are on order" is not an acceptable answer during an inspection.

Phase 5: Post-Commissioning (First Month of Operations)

  • Walk every zone with the signage schedule and verify 100% installation
  • Photograph every installed sign for audit records
  • Create a sign register (location, type, installation date, next inspection date)
  • Brief all workers on sign meanings during safety induction

Setting up a new factory? Send us your layout plans and we will provide a complete sign schedule with quantity, type, size, material, and cost for every location. Our new factory signage packages include everything from construction phase to commissioning.